Sunday, February 9, 2014

16 weeks house update

The columns and railing in our Master balcony got installed this week.



Our electrical wiring and lighting is about half installed now, and should be finished mid-week.

Wiring on Blake's wall.  On the other side is out hallway, and behind that is our Master.



Electric wiring in our Master, which will be on the left side of our bed.

LED housing, plumbing and HVAC in Colton's ceiling


We also got our double garage door installed, which will be a large space when opened to get our ride-one mower or ATVs (hopefully!) outside.



Saturday, February 1, 2014

15 Weeks house update

In the past 2 weeks, our HVAC system, fireplace, and plumbing got installed.

Family Room

Powder Room sink

HVAC in attic above Colton's Room

Kitchen sink wall

More HVAC above Master Bedroom

Kitchen range wall

Basement gym